
|
Date :
12 May 2005
Project :
PERMANENT SHEET PILING
AND GROUND ANCHOR
SYSTEM ALONG WALL 4 AND
WALL 8
ESC Client :
JABATAN KERJA RAYA
MALAYSIA AND
AHMAD ZAKI SDN BHD
Jalan Duta site office
Jalan Khidmat Usaha
Off Jalan Duta
50490 Kuala Lumpur |
| |
|

|
Title :
PROJECT REPORT
Contractors :
ESC PROJECTS (M) SDN BHD
Unit 41-3 Block G
Jalan PJU 1/37 Dataran Prima
47301 Petaling Jaya
Tel : 603-7880 2215
Fax : 603 7880 2704 |

Earth Support Company (M) Sdn Bhd (ESC) was established in 1994 (and
forms the manufacturing arm of the ESC Group) in Malaysia by a group of
engineers and contractors who realised that there were major drawbacks with
the sheet pile products and service available at the time. By combining
experience and technical knowledge, they found that most of these problems
could be solved, and with this incentive ESC set out to revolutionise the sheet
piling industry.
Sheet piles have been commonly used in the construction industry since early
last century. They are used in a wide variety of both temporary and permanent
building applications, including retaining walls, slope stabilisation, seepage
control barriers, river and canal frontages, quays, wharves, sea walls, dock and
harbour works, permanent foundations and ground reclamation works.
Since the implementation of the sheet-piling concept, the understanding and
knowledge of designing and constructing such structures has increased
significantly, both theoretically and practically. The design of the piles themselves
has remained relatively unchanged. Therefore while an engineer may have
greater insight into the problems faced and the possible solutions, eventually he
is forced to curtail his design to match the capabilities of existing available piles.
The ESC sheet pile (ESC PILE ) concept seeks to remove this handicap. Using the
experience gained by the construction industry over the last century, ESC have
identified and addressed the common problems associated with sheet piles, and
designed a new sheet pile that utilises the latest advances in construction and
geotechnical science. The ESC sheet-piling concept will provide engineers the
power to select a pile that will meet his or her requirements.
ESC sheet piles are the only Malaysian produced sheet piles available in the
market today. A proven product that has been successfully used since 1994 in
numerous prestigious projects, the ESC sheet pile is a Malaysian product that will
revolutionise a traditionally conservative industry.
ESC Projects (M) Sdn. Bhd. (ESC’s construction arm), carried out a project
recently in Kuala Lumpur, Malaysia for the Jabatan Kerja Raya, Malaysia (Public
Works Department of Malaysia) where ESC sheet piles were used in a permanent
situation. This allowed for faster construction time, lower cost and an
aesthetically pleasing finished product.
The project was:
PROJEK MENAIKTARAF JALAN DUTA, JALAN KUCHING DAN JALAN-JALAN
HUBUNGAN LAIN DI KUALA LUMPUR
ESC’s scope was to provide the design, supply and construction of the complete
retaining wall and the associated ground anchors for the sections with greater
exposure. The design is based on a permanent sheet pile system that is
supported by permanent ground anchors at W4 and permanent cantilever wall
system at W8. The objectives of the system were;
1) To stabilise the existing
slope in the long term
against slides and
movement caused by
the additional
engineering loads
(backfill) on top of it and
the subsequent traffic
flow. |

Wall 4 before construction
|
The geotechnical analysis will determined the requirements of the sheet pile
retaining wall and anchoring system. The parameters determined were;
1) Earth and groundwater pressures
2) Structural forces
3) Settlements and displacements
Standards used in this section are;
BS 8002: Code of practice for earth retaining structures

Wall 4 during sheet pile installation

Wall 4 during anchor installation
Soil parameters were obtained from the borelogs. For wall W4, the results from
the Standard Penetration Test indicated that there was a hard impenetrable
layer varying from 9.0m to 12.0m from top of the road finished level, where the
Very Dense Sand and Hard Silt layers are found. Therefore, the required
embedment for 9.0m piles should be achieved with the usage of high frequency
vibro hammer and / or hydraulic drop hammer. Different values of f’ were used
for wall W8. This is due to the actual soil conditions on site are much higher than
the conditions indicated in soil log. The existing slope with the range of 26.5° -
29.1° steepness could actually stand up stably by itself with the existing soil
conditions, which means that the soil frictions on site must be sufficiently high.
Moreover the available bore log was carried out 3 years ago about 20m away
from wall W8.
- An analysis of the entire retaining wall system was carried out using
the ReWaRD Retaining Wall software.

In accordance with BS8002, the following considerations were made to the
analysis of the retaining wall in order to comply with the limit state design
requirements;
- Minimum over excavation of 0.5m
- Minimum surcharge of 10 kPa
- Use of design soil parameters, which are defined as the
representative soil parameters divided by a mobilisation factor (M)
of 1.2 (effective stress design). Table 2.4.1 and 2.4.2 show the values
for the design soil parameters.

Completed Wall 4

Completed wall 4
During all analysis, active water tables were set conservatively at 1.2m depth on
retained side and passive water tables at 0.5m depth on excavated side for wall
W4. While wall W8, the active and passive water table were set at 6.0m below
the finished road level, since wall W8 is located on top of an embankment.
In accordance with BS 8081 the anchor load design was done in compliance
with working load design, therefore the representative soil parameters are used
in the analysis of the required anchor loadings.
Due to the different soil conditions required to satisfy the different codes, two
cases were analysed of the structure using the ReWaRD software;

Wall 8 before construction
- SP case to determine sheet pile requirements (BS 8002)
- ANC case to determine anchor loadings (Eurocode –
Serviceability)
While Wall W8 was analysed using the most critical case (Section on Ch 30.00),
with the highest retained soil and steepest slope profile. And the largest factored
bending moment recorded was 56.7kNm/m. Please refer to Appendix B for
ReWaRD analysis results.

Wall 8 in progress
The retaining wall design will consist of two major components;
- Main Wall Sheet Piles
- Ground Anchor System

Standards used in this Section are;
BS 5950: Code of practice for structural use of steelwork in building
BS 8002: Code of practice for Earth retaining Structures
BS 8081: Code of practice for Ground Anchorages
BS 449: Specification for the use of structural steel in building

Completed construction Wall 8
The moment capacity of the Main Wall is based on;
Mc = fy* Z
Where;
Mc = ultimate design moment capacity
Z = section modulus
fy = material yield strength
= 180 N/mm2 for permanent piles
The ground anchors to be used are 400kN working load capacity anchors.
The preliminary designs for wall W4 were carried out based on the
following sequences of works:-
i. Installation of the sheet piles.
ii. Backfill to the ground anchorage level at the back of sheet pile
wall.
iii, Installation of ground anchors and RC waler
iv. Backfill to the finished road level
v. Construction of the capping beam.
And the preliminary designs for wall W8 were carried out based on the
following sequences of works:-
i. Installation of the sheet piles.
ii. Backfill at the back of sheet pile wall up to the finished road level.
iii. Construction of the capping beam.
ESC Projects ( M) Sdn. Bhd provides the Client with complete solutions to their
retaining wall needs. The experience gained in the last 10 years have allowed
the company to provide basement, marine, retaining and many other sheet pile
solutions to markets in Malaysia and overseas.
For all your sheet pilling solutions, please contact us at :
escprojects@escpile.com
and feel free to view our website at :
http:// www.escpile.com
“ We T a k e T h e P r e s s u r e , S o Y o u D o n ’ t H a v e T o “ |