Strengthening and enlargement of Nanyang Pond was part of the Kuala Lumpur Flood Mitigation Project, Package B which was awarded to PECD Berhad. ESC has been the main supplier of steel sheet piles with scope of work included supply and installation. Here ESC sheet piles were installed and then a concrete façade wall was constructed in front of the sheet piles as part of the Engineers Design.
The project was completed in February 2005.
| Project Details: |
| Client |
Jabatan Pengairan dan Saliran Malaysia |
| Main Contractor |
PECD Berhad |
| Sheet Pile Type |
ESC 20A S275 JRC in 12.0m lengths |
| Sheet Pile Quantity |
342 tons |
|