An open well was required at the base of one of the cracker unit cooling towers. ESC supplied and drove a sacrificial sheet pile wall and supported it with a single ring beam located at the top of the piles. Excavation depth was 5m with a high water table.
| Project Details: |
| Client |
Titan (M) Sdn Bhd |
| Main Contractor |
Fieldwork Engineering Sdn Bhd |
| Specialist Sub Contractor |
ESC Projects (M) Sdn Bhd |
| Sheet Pile Tonnage |
25 |
| Strutting Tonnage |
6 |
|