Al Jeer Fishing Harbour, Ras Al Khaimah, United Arab
Emirates
Project Description
The Government of Ras Al Khaimah needed to improve their harbour and berthing facilities for
the local fishing fleets. The decision was made to construct a shallow water quay wall in the Al
Jeer Harbour. The requirement was for a permanent quay wall with a dredge depth of -8.0 for
fishing vessels. Durability was for 50 years. All designs were to be as per the British Standards.
The Port Authorities considered several options, including suspended decks and concrete block
walls, however due to economics and timing, ESC’s sheet pile wall solution with tie rods won the
contract.
ESC carried out the alternative design calculations on behalf of the Contractor (Athena SA) and
submitted them for approval to the Client (RAK Government) and their Consultant (Gibb Ltd).
All relevant drawings and engineering detailing was provided by ESC for this project. Once
approval was received the manufacturing was carried out in the ESC factory for delivery to the
site.
As always, ESC personnel were on site to assist Athena SA during the beginning of the
installation process. Several recommendations were made regarding piling guides and handling
processes. ESC provided efficient Dawson Lifting Shackles that helped increase the productivity
of the installation, while ensuring maximum safety during the process.

Figure 1 Initial deadman sheet pile wall installation begins on site
Soil Profile
The existing seabed was between approximately -2.0 EL to +1.0 EL in the vicinity of the
proposed wall. Subsequent filling activity has reclaimed the area to approximately +3.0 EL. Fill
material is dense to very dense sandy gravel with cobbles and boulders.
The original seabed is a layer of medium dense to very dense silty sand, overlying a medium
dense to very dense silty gravel layer with sandstone bands up to 8.0m thick.
Below the gravel layer are pockets of medium dense to dense sands, overlying a very dense sand
layer with sandstone bands at approximately -13.0EL.

Figure 2 Now the main wall sheet pile installation starts
Structural Specifications for Sheet Piles
The specifications for the proposed Main Wall and the Anchor Wall piles are as follow:
| WALL
TYPE |
PILE TYPE |
PILE
LENGTH |
DESIGN
STRESS
(N/mm2) |
MAX. SECTION
MODULUS
(cm3/m) |
| Main Wall |
ESC46A
(6268) |
10.5m |
355 |
4040 |
| Anchor Wall |
ESC18A |
3.0m |
275 |
1800 |
The total sheet pile tonnage supplied was 920 tons. Pile shoes were fitted to all Main Wall piles
due to the hard driving conditions.
The tie rods were supplied by Dextra Manufacturing under the guidance and design of ESC. The
rods supplied were M47mm of steel grade 950/1050 at 3.0 metre centres in 15.0 metre lengths.
Tie rods were wrapped in Denso tape prior to installation.

Figure 3 Installation of the Main Wall before the Drop Hammer for final penetration

Figure 4 Tie Rod Installation is underway
Coating Requirements
The specified coating for the sheet piles is for sand blasting to SA2.5 followed by 50 micron of
primer and then 400 micron of coal tar epoxy paint. The coating is to be applied to the entire front
surface and two metres of the back surface of the Main Wall piles only.
Installation Details
Installation was done by pitching the sheet piles in a piling frame and driving to refusal with an
ICE 815 vibro hammer. Piles were then driven to the final required level using an IHC S90
hydraulic hammer, together with a pile helmet.

Figure 5 Typical cross section of sheet pile

Figure 6 Finishing Compaction Works Begins

Figure 7 Ready Final compaction continues now that all sheet piles and tie rods are installed

Figure 8 Finishing touches and its ready for commercial use |